Pioneer Power Inc. ×
  • Services
    • Overview
    • Pipe Fabrication
    • Pipefitting
    • Metal Fabrication
    • HVAC
    • Plumbing
    • Project Management
    • Maintenance
  • Markets
  • Projects
  • Quality & Safety
  • About
  • Contact
  • Bid Information
  • Upcoming Projects
Pioneer Power > Projects > Olmsted County District Energy System East Phase 1
  • Olmsted County District Energy System East Phase 1
  • Olmsted County District Energy System East Phase 1
  • Olmsted County District Energy System East Phase 1
Previous 1/3 Next

Olmsted County District Energy System East Phase 1

OWNER: Olmsted County
Market | Renewable energy
LOCATION:

Rochester, MN

STATUS:

Completed March 2010

PROJECT DURATION:

Eight months

Highlights

  • Fabricated and installed the steam, condensate and chilled-water piping from the Olmsted County Waste-to-Energy Facility to the county’s support services center, “Building 2117.”
  • The Waste-to-Energy Facility uses biomass fuel (i.e., trash) to produce steam based renewable energy to the Olmsted County District Energy System, providing the heating and cooling for “Building 2117.”
  • Project completed on time and under budget.
Next Project
Next Project
View Project List

Services

Project management, Pipe fabrication and installation,

Safety Performance

Zero OSHA recordable injuries or lost time accidents.

©2025 Pioneer Power, Inc.

2500 Ventura Drive | Woodbury, MN 55125

651-488-5561

  • Home  |  
  • Contact Us  |  
  • Privacy  |  

Pioneer Power has joined Limbach, a leading building system solutions firm that specializes in revitalizing and maintaining budding systems in existing facilities, ensuring your buildings are always ready to perform when it matters most.

Please note that your services and contacts will remain the same, but you will now have access to additional resources as part of the Limbach family.

Learn More About Our Services Contact Our Team Learn More About the Acquistion