Pioneer Power > Projects > Olmsted County District Energy System East Phase 1
  • Olmsted County District Energy System East Phase 1
  • Olmsted County District Energy System East Phase 1
  • Olmsted County District Energy System East Phase 1
Previous 1/3 Next

Olmsted County District Energy System East Phase 1

OWNER: Olmsted County
Market | Renewable energy
LOCATION:

Rochester, MN

STATUS:

Completed March 2010

PROJECT DURATION:

Eight months

Highlights

  • Fabricated and installed the steam, condensate and chilled-water piping from the Olmsted County Waste-to-Energy Facility to the county’s support services center, “Building 2117.”
  • The Waste-to-Energy Facility uses biomass fuel (i.e., trash) to produce steam based renewable energy to the Olmsted County District Energy System, providing the heating and cooling for “Building 2117.”
  • Project completed on time and under budget.
Next Project
Next Project
View Project List

Services

Project management, Pipe fabrication and installation,

Safety Performance

Zero OSHA recordable injuries or lost time accidents.